50MW Olives Farm gets consent
Subject to re-confirming the connection costs SSL intends to acquire this project by Q3 2024, construct a 2 hour BESS, and achieve energisation in 2026
Subject to re-confirming the connection costs SSL intends to acquire this project by Q3 2024, construct a 2 hour BESS, and achieve energisation in 2026
Acquisition expected Q3 2024 and energisation in 2026 PHOTO—Layout
Solos hosted a delegation of Korean investors led by Shinhan Asset Managament
PHOTO—BATTERIES GOING in
Dept of Industry and Trade for both countries sign an MOU committing significant investment to UK and re-inforcing Shinhans prominent role PHOTOPETER PAUL at MANSION HOUSE
This projects brings Shinhan’s investment to 135MW 2 hour systems
Foundation stage completion---PHOTO OF FOUNDATIONS
Solos attend an investor Forum hosted by Shinhan with CMS and Samsung in Seoul , Korea
LS Electric as main ECP and Suir Engineering as lead sub-contractor commence construction on 50MW 2 hour BESS.
The project is arranged using the new QAHC structure.